And there seems to have also been a mishap on Chetumal Bouelvard. IT was just opened on Monday, but already the concrete surface is showing significant cracking in one area. This morning when we passed, we saw workers with a jackhammer, breaking open the surface to concrete certain areas again. The City Council press officer Kenny Morgan told us that there is an area of 30 feet where cracks had occurred. He says according to the city engineer, those are expected over that distance of road, where defects will come up. He says the City Engineer has given assurances that it is nothing that will compromise the integrity of the concrete slab. But at least one engineer we've spoken with differs; he says it is a significant event because the crack will allow water to infiltrate the concrete and undermine the foundation.
We note that this contractor is the same one who did Evergreen Street behind BWSL – which had to be patched in multiple places.