It was the last to get on line but Punta Gorda is finally unto the national power grid which should mean a more reliable power supply for that most Southern town. Under the power 4 project a 69 kilovolt transmission line now connects the Independence and Punta Gorda load centers to a control system based in Belize City. This connection now has the entire country with the exception of Caye Caulker linked to the national grid. BEL is now in the process of decommissioning the existing diesel generators in Punta Gorda.
Business
PG Gets Online with BEL
Punta Gorda is now connected to the national power grid, improving power supply reliability and allowing for the decommissioning of diesel generators.
Share
Tags
Punta Gorda
Belize City
BEL